Miller Plumbing
Customer
John Anderson
john.anderson@email.com
(407) 555-0192
Job site
24 Main Street
Orlando, FL
Scope of work
Replace a 50-gallon water heater.
| Description | Amount |
|---|---|
| 50 gal. water heater (Parts & Materials) | $1,350.00 |
| Labor & Professional Installation | $500.00 |
- Subtotal
- $1,850.00
- Sales Tax (6.0% materials)
- $81.00
- Total
- $1,931.00
- Required deposit (30%)
- $579.30
- Remaining balance
- $1,351.70
- Balance due
- Aug 24, 2026
Payment terms & deposit
A 30% deposit ($579.30) is required to approve this estimate and schedule the work.
The remaining balance ($1,351.70) will be due when the job is finished (Aug 24, 2026).
Eligible card processing fees may apply where permitted.
Project schedule
- Estimated Start
- Aug 20, 2026
- Expected Completion
- Aug 24, 2026
Dates shown are estimates, not guarantees.
Terms & conditions
Valid for the period shown above. Work begins after approval and any required deposit. Changes to scope, materials, or site conditions may require a written change order and adjusted pricing before additional work proceeds.
Licensed, insured, and bonded in Florida. Workmanship warranty as stated at completion; manufacturer warranties apply to equipment installed.
Licensed, insured, and bonded in Florida. Workmanship warranty as stated at completion; manufacturer warranties apply to equipment installed.
Acceptance & payment
This estimate may be accepted electronically through the secure payment link provided by the contractor. Payment of the required deposit constitutes acceptance of this estimate and the applicable Terms & Conditions, except where additional signatures or disclosures are required by applicable law.